Pensacola Beach Nourishment

Project Status Updates
5 MARCH 2026
Sand placement has commenced. Beach fill operations will progress eastward toward Park East.
• Dog parks remain open
Closures:
• Active work zone – Beach east of the Dog Park – East parking lot, 1,000 ft of shoreline (see map)
• Western parking lot at Park East (#29.1, at dune walkover 29B)
Please see the below interactive map for details and the current work areas.
26 FEBRUARY 2026
All four pipelines are in place and sand placement is expected to commence early next week.
19 FEBRUARY 2026
Pipelines #1, #2, and #3 are in place. Pipeline #4, located east of Dog Park – East, will be installed next week. Some equipment will be moved along the shoreline and the rest will be transported by truck from Park West to Park East in the coming days.
17 FEBRUARY 2026
Pipelines #1, #2, and #3 are in place. Pipeline #4, located east of Dog Park – East, is scheduled for installation tomorrow. Survey crews are currently on site documenting the pre-construction elevation of the beach. The contractor will be moving equipment along the shoreline from Park West to Park East.
12 FEBRUARY 2026
Pipelines #1, #2, and #3 are in place. Sand placement is delayed until March. The detailed schedule and order of work will be posted as soon as possible.
10 February 2026
Pipelines #1 and #2 are in place. Sand placement is delayed until March.
3 February 2026
Pipelines #1 and #2 are in place. Sand placement is delayed until later this month.
26 JANUARY 2026
Pipeline #1 was installed east of the Seahorse Condominium. Plans for this week include installation of Pipeline #2 near Avenida 10 and movement of equipment and materials into the northwest corner of the main Casino Beach parking lot, located at the intersection of Ft. Pickens Road and Via de Luna (see map below).
16 JANUARY 2026
Next week, small areas of the beach will see some activity as the contractor installs two of the four pipeline landings for the project. Pipeline #1 will be east of the Seahorse Condominium and pipeline #2 will be near Avenida 10.
2 JANUARY 2026
On January 2, equipment and materials will be moved to the beach area located east of Park West and near Dog Park – West. The dog park remains open.
29 DECEMBER 2025
The northwest corner of the Park West sound side parking lot (#21N) will be closed starting Monday, December 29th. The contractor will be storing equipment in this area. Equipment deliveries will begin Monday and continue in the coming days.

