Pensacola Beach Nourishment

PROJECT OVERVIEW

8.1 miles
1.5 million cubic yards of sand
3 months (estimated) to complete Local Sponsor:
Santa Rosa Island Authority Contractor:
Manson Construction Company

Project schedule

*All dates are subject to change as work is dependent on weather conditions and equipment

Last Updated: 18 MAY 2026

Post-Construction Activity
Removal of equipment and general site clean-up will continue over the coming weeks.  Tilling is expected to occur on Friday, May 22nd, from Park West to Casino Beach.